Shelter the Homeless
Meet Joseph
Background Details:
71 year old Misago Joseph looks after 2 orphaned grandchildren. His house was ruined by heavy rains. After a visit last week to the Kiwaala community, Moses identified this project as being a priority. The project is to construct a house for Joseph and the children. After all, don't we as parents of children, want children to be raised and nurtured in a safe and healthy home.
On October 13, 2012 Moses and a group of youth will construct a house for Joseph and the children from donated bricks (thank you to the Kiwaala Community Chairman). My commitment will be to fund the purchase of additional materials so this priority proceeds on this date.
Let us make this project happen so this family can sleep well each night.
Details: Items required
* 5000 Bricks donated by the Community Chairman
* Construction labour supplied by Moses and Kitovu LifeTeen youth
* 13 Iron sheets UGX 260 000
* 1 Door UGX 50 000
* 2 Windows UGX 60 000
* 1 kg Nails UGX 5 000
* 8 Ventilators UGX 8 000
* 5 Poles UGX 20 000
Total Costs = UGX 403 000 converted to AUS $ 158.00
Report:
71 year old Misago Joseph looks after 2 orphaned grandchildren. His house was ruined by heavy rains. After a visit last week to the Kiwaala community, Moses identified this project as being a priority. The project is to construct a house for Joseph and the children. After all, don't we as parents of children, want children to be raised and nurtured in a safe and healthy home.
On October 13, 2012 Moses and a group of youth will construct a house for Joseph and the children from donated bricks (thank you to the Kiwaala Community Chairman). My commitment will be to fund the purchase of additional materials so this priority proceeds on this date.
Let us make this project happen so this family can sleep well each night.
Details: Items required
* 5000 Bricks donated by the Community Chairman
* Construction labour supplied by Moses and Kitovu LifeTeen youth
* 13 Iron sheets UGX 260 000
* 1 Door UGX 50 000
* 2 Windows UGX 60 000
* 1 kg Nails UGX 5 000
* 8 Ventilators UGX 8 000
* 5 Poles UGX 20 000
Total Costs = UGX 403 000 converted to AUS $ 158.00
Report: